Download Market Announcement - Maamba Energy Limited 300 MW Phase II Power Plant Project
Market Announcement - Maamba Energy Limited 300 MW Phase II Power Plant Project
Published Date: 5th September 2024
Shareholders are referred to the announcement dated 10th July 2024 wherein the Board of ZCCM Investments Holding Plc (“ZCCM-IH” or the “Company”) informed shareholders and the market that Maamba Energy Limited (“MEL”), formerly Maamba Collieries Limited, had reached an agreement with anchor lenders regarding the financing for the construction and installation of an additional 300-Megawatt power plant at MEL (“the Project”). It was further indicated that the total estimated cost of the Project is USD 400 million, of which approximately USD 300 million will be financed by a consortium of lenders. ZCCM-IH will contribute USD 15 million towards the debt portion in form of a loan that will have a tenor of 10.25 years from construction start inclusive of a moratorium of 3.25 years. The interest rate will be nine per cent per annum.